Modebest logo
24 years

Brook Avenue, Wembley

Client: Mulalley
Value: £3.75M
Duration:Nov 2013 – Apr 2014
Project Type: Groundwork and RC Frames

Project Description

Remediation of the existing ground followed by the construction of 3 number 9 storey reinforced concrete frames and 1 number 6 storey reinforced concrete frame parallel to the London Underground railway tracks adjacent to Wembley Park Station.

Scope of Works

Groundworks commenced in November 2013, with the RC frames due for completion in April 2014, based on an overall agreed programme duration of 35 weeks. We handed over the works 5 weeks early.


Following careful planning and close liaison between TFL, London Underground, Mulalley and ourselves we were able to work closely with all parties to agree a strategy that we could implement in order to construct the works safely and in a logical sequence. This was key to ensuring that all stakeholders were confident signing off method statements and also that all parties were fully conversant with the lifting plans, exclusion zones, tower crane restrictors and the logistics that were signed off to allow us to complete the works. This included daily reviews on site to ensure that no loose materials or debris could breach the neighbouring railway lines.


The site was initially remediated and then the enabling works were carried out including retaining walls and temporary access routes which were all completed prior to our main works commencing. The foundations were piled by others and then our groundworks commenced on the blocks in an agreed sequential manner.


The superstructure comprised 3 number 9 storey reinforced concrete blocks and 1 number 6 storey reinforced concrete block, using 800 Tonne of cut & bent reinforcement and 6,000 M3 of concrete.


External works were completed following the fitting of the brickwork façade and internal fit outs. This included the permanent road into site constructed using permeable pavement construction, stone filled gabions to retain the banks to the road side elevation, block paving and topsoil to communal areas and patios.



 

Back...

 

orange stripes

0

Current Workforce

0

Projects Completed

0

Offices

Latest News

16th September 2018

Charity Bicycle Run from London to Brighton

Modebest team take part in demanding cycle run from Clapham Common to Brighton in aid of Centrepoint Read more...

5th September 2018

DIY SOS GRENFELL

Modebest Builders are proud to be supporting the BBC DIY SOS programme as they build a brand-new home for the Dale Youth Boxing Club. Read more...

14th May 2018

Modebest has Moved to Brand New Premises

Modebest is proud to announce that we have constructed bespoke brand-new premises which we have called ‘MOY HOUSE’. Read more...

27th April 2018

We Are Moving

Modebest is moving to brand new premises with effect from 14th MAY 2018 Read more...

“We are committed to enhancing our company’s image and profile in the market place by addressing issues relating to corporate and social responsibility”

  • Achilles
  • Lighthouse Charity
  • Women into Construction
  • SMAS
T: + 44 (0) 20 8900 1981  |  F: + 44 (0) 20 8903 5238  |  E: info@modebest.co.uk
Specialists in: Groundworks | RC Frames | Civil Engineering
Specialists through: Expertise | Innovation | Competence | Safety