Modebest logo
23 years

Brook Avenue, Wembley

Client: Mulalley
Value: £3.75M
Duration:Nov 2013 – Apr 2014
Project Type: Groundwork and RC Frames

Project Description

Remediation of the existing ground followed by the construction of 3 number 9 storey reinforced concrete frames and 1 number 6 storey reinforced concrete frame parallel to the London Underground railway tracks adjacent to Wembley Park Station.

Scope of Works

Groundworks commenced in November 2013, with the RC frames due for completion in April 2014, based on an overall agreed programme duration of 35 weeks. We handed over the works 5 weeks early.


Following careful planning and close liaison between TFL, London Underground, Mulalley and ourselves we were able to work closely with all parties to agree a strategy that we could implement in order to construct the works safely and in a logical sequence. This was key to ensuring that all stakeholders were confident signing off method statements and also that all parties were fully conversant with the lifting plans, exclusion zones, tower crane restrictors and the logistics that were signed off to allow us to complete the works. This included daily reviews on site to ensure that no loose materials or debris could breach the neighbouring railway lines.


The site was initially remediated and then the enabling works were carried out including retaining walls and temporary access routes which were all completed prior to our main works commencing. The foundations were piled by others and then our groundworks commenced on the blocks in an agreed sequential manner.


The superstructure comprised 3 number 9 storey reinforced concrete blocks and 1 number 6 storey reinforced concrete block, using 800 Tonne of cut & bent reinforcement and 6,000 M3 of concrete.


External works were completed following the fitting of the brickwork façade and internal fit outs. This included the permanent road into site constructed using permeable pavement construction, stone filled gabions to retain the banks to the road side elevation, block paving and topsoil to communal areas and patios.



 

Back...

 

orange stripes

0

Current Workforce

0

Projects Completed

0

Offices

Latest News

1st December 2016

Modebest are awarded Thorn Turn site safety award, November 2016 from Morgan Sindall

Our operative, Ioan-Iulian Costan won the Thorn Turn, Highways Depot project Health and safety award for November 2016. Read more...

27th October 2016

Modebest win major CONSTRUCT Award

Modebest are proud to have won a CONSTRUCT Innovation Award at the annual awards during October 2016. Our project at Abbey Mills, Shaft F, for our client MVB Joint Venture, was the overall winner in the category of Projects over £2.50M that exemplify innovation and people talent in the concrete sector. Read more...

1st September 2016

Modebest has recently commenced work on a civil engineering project at Thorn Turn Waste Park & Highways Depot, Houghton Regis, Bedfordshire for Morgan Sindall

Modebest are delighted to have recently been awarded a civil engineering contract by our client Morgan Sindall for a project, Thorn Turn Waste Park & Highways Depot. Read more...

25th July 2016

Summary of Archaeological Finds on our Design & Build project at Fulham High Street

Modebest are engaged as a Principle Contractor for a Design & Build project at Fulham High Street. The project is for the Enabling and Archaeological works incorporating sheet piling to the basement, bored piling, basement excavation and reinforced concrete foundations. Read more...

“Our vision is to be a company that our clients will want to work with, rely on and that our personnel will be proud to work for. A company with an open mind ready to embrace new opportunities, innovative and driven to deliver a safer, low carbon and sustainable product”

T: + 44 (0) 20 8900 1981  |  F: + 44 (0) 20 8903 5238  |  E: info@modebest.co.uk
Specialists in: Groundworks | RC Frames | Civil Engineering
Specialists through: Expertise | Innovation | Competence | Safety

Modebest Builders Ltd

Unit 2,
29 Fourth Way,
Wembley,
Middlesex,
HA9 0LH, UK