Grand Union Centre, Ladbroke Grove

Client: John Sisk & Son Ltd
Value: £6.90M
Duration:Feb 2014 – Jan 2015 48 Weeks
Project Type: Groundwork and RC Frames

Project Description

The project entailed the construction of a residential and commercial mixed used scheme comprising 133 number residential units, in 2 number six storey blocks of private flats and 2 number six storey blocks of shared ownership/rented, and I number commercial block.


Scope of Works

We were engaged by Sisk as a domestic Sub-Contractor on an amended form of sub-contract, JCT Design & Build 2011 without any permanent works design responsibility. The basement temporary works were designed and installed by us.


The scope of works comprised reduce level dig excavation including site waste management and the removal of contaminated spoil, installation of piling mat and piling works attendance, excavation of a large basement, installation of temporary works, construction of reinforced concrete foundations and basement, installation of under-slab drainage, site-wide drainage and services incorporating surface water attenuation tanks and pumps, construction of undercroft car parking areas including tarmacadam works, construction of a shared RC podium transfer slab to all blocks and the construction of 4 number RC six storey low rise blocks including RC cores.




The scope of works entailed:

  • Bulk excavation and reduce level dig
  • Site waste management and non-hazardous contaminated spoil disposal
  • Piling mat installation and piling attendance
  • Design and installation of temporary works to the existing street elevation along Ladbroke Grove
  • Large basement excavation
  • Site logistics management
  • Provision of tower crane attendance personnel
  • Under-slab drainage
  • Site wide drainage and services
  • Storm water attenuation tanks and pump chambers
  • RC Substructures
  • RC Basement
  • Waterproofing systems
  • Undercroft carpark construction
  • Tarmacadam base course installation in order to facilitate falsework propping for the podium slab
  • RC podium transfer slab / deck – 2500m2
  • 4 number blocks, 6 storey high, low rise RC Frames
  • Second visit for the completion of the final drainage connections, tarmacadam surface wearing course and line marking to the undercroft carpark and for the construction of RC Stairs from podium level up to street level.

All of the works were completed on programme.


 

Back...

 

orange stripes

0

Current Workforce

0

Projects Completed

0

Offices

Latest News

16th September 2018

Charity Bicycle Run from London to Brighton

Modebest team take part in demanding cycle run from Clapham Common to Brighton in aid of Centrepoint Read more...

5th September 2018

DIY SOS GRENFELL

Modebest Builders are proud to be supporting the BBC DIY SOS programme as they build a brand-new home for the Dale Youth Boxing Club. Read more...

14th May 2018

Modebest has Moved to Brand New Premises

Modebest is proud to announce that we have constructed bespoke brand-new premises which we have called ‘MOY HOUSE’. Read more...

27th April 2018

We Are Moving

Modebest is moving to brand new premises with effect from 14th MAY 2018 Read more...

“We are committed to enhancing our company’s image and profile in the market place by addressing issues relating to corporate and social responsibility”

  • Achilles
  • Lighthouse Charity
  • Women into Construction
  • SMAS
T: + 44 (0) 20 8900 1981  |  F: + 44 (0) 20 8903 5238  |  E: info@modebest.co.uk
Specialists in: Groundworks | RC Frames | Civil Engineering
Specialists through: Expertise | Innovation | Competence | Safety