Golf Links Estate, Southall

Client: Durkan Ltd
Value: £2.30M
Duration:Feb, 2014 – Oct , 2014 Subs & RC Frames 36 Weeks
Project Type: Groundwork and RC Frames

Project Description

The project entailed the construction of 5 number blocks of terraced housing and 2 number blocks of 6 storey low rise reinforced concrete frames forming 36 number houses and 26 number flats.

Scope of Works

We were engaged by Durkan as a domestic sub-contractor on an amended form of Sub-Contract, NEC 3 Engineering and Construction. We supplied a tower crane and attendant crane personnel to Durkan for this project.



The scope of works comprised reduced level dig, installation of a piling mat and piling attendance to the RC frame blocks, site waste management and removal of spoil from site, excavation and pouring mass concrete foundations up to 3.0m deep for the terraced housing blocks, substructure brickwork up to air brick level and precast concrete block and beam flooring to five terraced housing blocks, RC foundations and RC core, underslab drainage, site-wide drainage and services, deep drainage and 278 works connecting into existing estate drainage, two number low rise RC Frames, 6 storeys high, one RC core, 6 storeys high, interlinking steel bridge between the RC Blocks with metal decking and structural concrete topping, external works to front and rear gardens and the formation of a new road within the estate.



The scope of work entails:

  • Installation of a piling mat and piling attendance
  • Reduce level dig and foundation excavation
  • Site waste management and spoil disposal
  • Site logistics management
  • Supplying a tower crane
  • Providing tower crane attendant personnel
  • Underslab drainage
  • Site-wide drainage and services
  • Deep drainage and Section 278 works connecting to existing estate drainage
  • Excavation and pouring mass concrete foundations up to 3.00m deep to the housing blocks
  • Substructure brickwork up to air brick level in the terraced housing blocks
  • Precast concrete block and beam flooring to the terraced housing blocks
  • RC foundations and RC core foundations
  • 2 number low rise RC Frames, 6 storeys high
  • 1 number RC core, 6 storeys high
  • Metal decking and structural concrete topping to link bridge
  • External works to front and rear gardens
  • New estate road




 

Back...

 

orange stripes

0

Current Workforce

0

Projects Completed

0

Offices

Latest News

14th May 2018

Modebest has Moved to Brand New Premises

Modebest is proud to announce that we have constructed bespoke brand-new premises which we have called ‘MOY HOUSE’. Read more...

27th April 2018

We Are Moving

Modebest is moving to brand new premises with effect from 14th MAY 2018 Read more...

27th April 2018

Modebest Fundraising Golf Day

Modebest Fundraising Golf Day in aid of the ‘Search for David Gavin Fund’ held at Sudbury Golf Course, Friday, 27th April 2018 Read more...

1st December 2016

Modebest are awarded Thorn Turn site safety award, November 2016 from Morgan Sindall

Our operative, Ioan-Iulian Costan won the Thorn Turn, Highways Depot project Health and safety award for November 2016. Read more...

“The company’s personality and culture is one of integrity, working ethically, ensuring that our client’s needs are foremost and creating a harmonious workplace that draws the best from people.”

T: + 44 (0) 20 8900 1981  |  F: + 44 (0) 20 8903 5238  |  E: info@modebest.co.uk
Specialists in: Groundworks | RC Frames | Civil Engineering
Specialists through: Expertise | Innovation | Competence | Safety

Modebest Builders Ltd

Moy House
69 Belvue Road
Northolt
Middlesex
UB5 5XS