Bow,
London, E15
Client
Morgan
Sindall
Value
£3m
Abbey Mills Shaft F is part of the Thames Tideway Tunnel, a 25km combined sewer that runs under River Thames and is designed to capture, store & convey all raw sewage that previously overflowed into the estuary.
Working in a confined space environment, Modebest sought many innovative methods to deliver a successful project, the pride of knowing the outcome would be a cleaner, healthier environment for everyone to enjoy.
Abbey Mills Shaft F Internal Structures consisted of slip forming a 1m thick reinforced concrete ‘H’ shaped spine wall structure (3100m³ of 6600 m³ RC concrete) within a 25metre diameter shaft, both supporting 1m thick RC slab on either side of the spine structure allowing incoming sewage to cascade to the bottom of this 70metre deep reception shaft & onwards to Beckton Sewage Treatment Works.
Completed in 2016, with safety being the utmost priority while working under Confined Space regulations, construction techniques included:
24/7 slipforming of internal vertical structures to incorporate sloping soffits & large structural openings (10no 8m x 4m opes & 16no 7m x 2m opes), Gass falsework to slabs while using precast support elements to eliminate forming 53m high falsework supports systems.