Fitzrovia
W1T
Client
Morgan
Sindall
Value
£14m
Completed in March 2024, the basement support consisted of modular hydraulic propping systems used in conjunction with ground movement monitors and berms. The frame comprised of 9 no. lift shafts and 3 no. stair cores constructed using traditional RC Frame construction methods. Complex falsework construction for RC Slab with a high number of steps and 45-degree slopes. Intricate reinforcement designs consisting of H40 couplers in beams, 325mm minimum thick slabs and thousands of couplers on every floor.
A logistically complex project with only one access located between 2 existing buildings one of which is listed. The design issues and complexity of the project required continuous resequencing and careful planning and monitoring.