Wandsworth,
London, SW18
Client
Hollybrook
Value
£9m

A mixture of Traditional Build, Slip Form Construction and Post-tensioning works, this was a project that required a detailed logistics plan from the outset. The works consisted of 3 blocks, ranging from 10 – 14 storeys high including a deep basement with an associated ramp and a large Podium area in Wandsworth, with the build covering the complete site footprint.
A watertight basement construction required the installation of flying shores and heavy-duty propping. In addition, a Gas membrane was required for the Ground floor areas. Two of the tower blocks were constructed utilising slipform construction with the other being formed traditionally. Post-tensioning construction was detailed for the upper floors together with Precast Concrete Columns from our in-house factory, ensuring the works were completed to a high standard.
Following the completion of the RC frames, External Works including Highway Works, were completed in a phased sequence to allow the following trades to complete their works. A particular feature of the External areas was the high-quality finish precast planters formed in the open space areas.